NT Wide Program

The NT Wide Initiatives Program, aimed at improving water, power and sanitation across Northern Territory homelands, has been allocated $2 million per annum for 3 years (2024-2027) under the HHIP, funded by the Australian Government.

Service provider/contractor Deltareef Pty Ltd
Proposed work Upgrades to existing hybrid power / solar system in Birany Birany homeland
Grant value (excluding GST) $294,855
Current statusWorks completed January 2026
Completion reportRead the Birany Birany completion report PDF (2.2 MB)
Service provider/contractor DICE (AUST) Pty Ltd
Proposed work Upgrades to septic systems in Myatt homeland
Grant value (excluding GST) $124,231
Current statusWorks completed November 2025
Completion reportRead the Myatt completion report PDF (9.7 MB)
Service provider/contractor Ingkerreke Services Aboriginal Corporation
Proposed work Upgrades to sanitation systems in Arrilhjere, Tnerte, Shannon Bore and Boomerang Bore homelands
Grant value (excluding GST) $137,376
Current status Due for completion by September 2025
Service provider/contractor Bush Grid Pty Ltd
Proposed work Upgrades to solar power systems in Ganpura homeland
Grant value (excluding GST) $135,795
Current statusWorks completed May 2025
Completion reportRead the Ganpura completion report PDF (1.6 MB)
Service provider/contractor Warddeken Land Management Ltd
Proposed work Construction of new ablution in Kabulwarnamyo homeland
Grant value (excluding GST) $147,974
Current statusWorks completed November 2025
Completion reportRead the Kabulwarnamyo completion report PDF (4.3 MB)
Service provider/contractor Barkly Plumbing Services
Proposed work Construct and install new bore at Wiitin homeland
Grant value (excluding GST) $134,982
Current statusWorks completed September 2025
Completion reportRead the New Wiitin Bore completion report PDF (7.4 MB)
Service provider/contractor
Tiwi Islands Regional Council
Proposed work
Sanitation upgrades across Tiwi Islands homelands
Grant value (excluding GST)
$250,000
Current status
Works commenced November 2025
Service provider/contractor
Yapa-Kurlangu Ngurrara Aboriginal Corporation
Proposed work
Solar power refit in Urlampe homeland
Grant value (excluding GST)
$156,055
Current status
Works completed July 2025
Completion reportRead the Urlampe Solar Upgrade completion report PDF (1.3 MB)
Service provider/contractor
Ecoenergy Australia Pty Ltd
Proposed work
Solar power refit in Kulpitharra homeland
Grant value (excluding GST)
$126,100
Current status
Works completed November 2025
Completion reportRead the Kulphitarra completion report PDF (1.6 MB)
Service provider/contractor
Advanced Plumbing and Gas Services
Proposed work
Septic upgrades in Ilpurla homeland
Grant value (excluding GST)
$31,831
Current status
Works completed May 2025
Completion reportRead the Ilpurla completion report PDF (1.7 MB)
Service provider/contractor
Bush Grid
Proposed work
Installation of generator in Banthula homeland
Grant value (excluding GST)
$131,781
Current status
Works completed June 2025
Completion reportRead the Banthula completion report PDF (1.7 MB)
Service provider/contractor
Ecoenergy Australia Pty Ltd
Proposed work
Solar power system upgrade in Double D homeland
Grant value (excluding GST)
$82,047
Current status
Works completed November 2025
Completion reportRead the Murray Downs completion report PDF (2.4 MB)
Service provider/contractor
Laynhapuy Homelands Aboriginal Corporation
Proposed work
Installation of solar power system in Burrum homeland
Grant value (excluding GST)
$123,640
Current status
Works completed August 2025
Completion reportRead the Burrum house completion report PDF (1.7 MB)
Service provider/contractor
Tiwi Islands Regional Council
Proposed work
Solar System upgrade - Paru
Grant value (excluding GST)
$47,500
Current status
Works completed September 2025
Completion reportRead the Paru completion report PDF (3.7 MB)
Service provider/contractor
Yilli Rreung Housing Aboriginal Corporation
Proposed work
New Generator - Walangurrminy
Grant value (excluding GST)
$35,586
Current status
Works completed August 2025.
Completion reportRead the Walangurrminy generator upgrade completion report PDF (830.1 KB).
Service provider/contractor
McMinns Bore
Proposed work
New Bore - Fitzroy Station
Grant value (excluding GST)
$13,850
Current status
Works completed November 2025
Completion reportRead the Bore Overview Fitzroy Station completion report PDF (4.8 MB)
Service provider/contractor
Warnbi Aboriginal Corporation - Kakadu
Proposed work
Patonga Airstrip and Mamukala - Water Filtration
Grant value (excluding GST)
$23,985.33
Current status
Due for completion by September 2026
Service provider/contractor Bush Grid Pty Ltd
Proposed work Upgrades to Solar Power to Gunpura
Grant value (excluding GST) $135,769
Current statusDue for completion by August 2026
Service provider/contractor Bullant Building  
Proposed work Mulga Bore - Sanitation Upgrades  
Grant value (excluding GST) $140,000  
Current statusWorks completed September 2025 
Completion reportRead the Mulga Bore Sanitation Upgrades completion report PDF (7.8 MB) 
Service provider/contractor Yapa-Kurlangu Ngurrara Aboriginal Corporation
Proposed work Bonya - Electrical Upgrades
Grant value (excluding GST) $255,218
Current statusDue for completion by June 2026
Service provider/contractor Territory Water Solutions
Proposed work Burudu - Solar Power Repair
Grant value (excluding GST) $242,165
Current status Due for completion by August 2026
Service provider/contractor Territory Water Solutions
Proposed work Jemelke - Bore and Water Works Upgrades
Grant value (excluding GST) $35,209
Current statusWorks completed January 2026
Completion reportRead the Jemelke Bore and Water Works Upgrades completion report PDF (2.2 MB)
Service provider/contractor Urapuntja Aboriginal Corporation
Proposed work Soapy Bore and Atheley – New Waste Site
Grant value (excluding GST) $84,000
Current statusDue for completion by August 2026
Service provider/contractor M.G. Electrical Services Pty Ltd
Proposed work Mulga Bore - Powerline Extension
Grant value (excluding GST) $346,210
Current statusDue for completion by August 2026
Service provider/contractor Yilli Rreung Housing Aboriginal Corporation
Proposed work House 5 Wariuk
Grant value (excluding GST) $65,000
Current statusDue for completion by August 2026
Service provider/contractor Warnbi Aboriginal Corporation
Proposed work Mudginberri – Bore Works
Grant value (excluding GST) $51,603
Current statusDue for completion by August 2026
Service provider/contractor Ngaliwurru-Wuli Aboriginal Corporation
Proposed work Brumby Plains – Septic Upgrades
Grant value (excluding GST) $35,000
Current statusDue for completion by August 2026
Service provider/contractor Think Water Alice Springs
Proposed work Wild Plum and Jemelke – Solar Bore and Generator Works
Grant value (excluding GST) $96,612
Current statusDue for completion by August 2026
Service provider/contractor Territory Water Solutions
Proposed work Burudu – Solare Bore
Grant value (excluding GST) $115,000
Current statusDue for completion by August 2026
Service provider/contractor Laynhapuy Homelands Aboriginal Corporation
Proposed work Bukudal – Septic and Water Tank
Grant value (excluding GST) $72,635
Current statusDue for completion by August 2026
Service provider/contractorMcMinns Bore Services
Proposed workFitzroy Station – Bore Works
Grant value (excluding GST)$16,820
Current statusDue for completion by August 2026
Service provider/contractorBawinanga Homelands Aboriginal Corporation
Proposed workUpgrades to Power System in Ji-Marda Homeland
Grant value (excluding GST)$212,760
Current statusDue for completion by August 2026