NT Wide Program
The NT Wide Initiatives Program, aimed at improving water, power and sanitation across Northern Territory homelands, has been allocated $2 million per annum for 3 years (2024-2027) under the HHIP, funded by the Australian Government.
| Service provider/contractor | Deltareef Pty Ltd |
|---|---|
| Proposed work | Upgrades to existing hybrid power / solar system in Birany Birany homeland |
| Grant value (excluding GST) | $294,855 |
| Current status | Works completed January 2026 |
| Completion report | Read the Birany Birany completion report PDF (2.2 MB) |
| Service provider/contractor | DICE (AUST) Pty Ltd |
|---|---|
| Proposed work | Upgrades to septic systems in Myatt homeland |
| Grant value (excluding GST) | $124,231 |
| Current status | Works completed November 2025 |
| Completion report | Read the Myatt completion report PDF (9.7 MB) |
| Service provider/contractor | Ingkerreke Services Aboriginal Corporation |
|---|---|
| Proposed work | Upgrades to sanitation systems in Arrilhjere, Tnerte, Shannon Bore and Boomerang Bore homelands |
| Grant value (excluding GST) | $137,376 |
| Current status | Due for completion by September 2025 |
| Service provider/contractor | Bush Grid Pty Ltd |
|---|---|
| Proposed work | Upgrades to solar power systems in Ganpura homeland |
| Grant value (excluding GST) | $135,795 |
| Current status | Works completed May 2025 |
| Completion report | Read the Ganpura completion report PDF (1.6 MB) |
| Service provider/contractor | Warddeken Land Management Ltd |
|---|---|
| Proposed work | Construction of new ablution in Kabulwarnamyo homeland |
| Grant value (excluding GST) | $147,974 |
| Current status | Works completed November 2025 |
| Completion report | Read the Kabulwarnamyo completion report PDF (4.3 MB) |
| Service provider/contractor | Barkly Plumbing Services |
|---|---|
| Proposed work | Construct and install new bore at Wiitin homeland |
| Grant value (excluding GST) | $134,982 |
| Current status | Works completed September 2025 |
| Completion report | Read the New Wiitin Bore completion report PDF (7.4 MB) |
Service provider/contractor | Tiwi Islands Regional Council |
|---|---|
Proposed work | Sanitation upgrades across Tiwi Islands homelands |
Grant value (excluding GST) | $250,000 |
Current status | Works commenced November 2025 |
Service provider/contractor | Yapa-Kurlangu Ngurrara Aboriginal Corporation |
|---|---|
Proposed work | Solar power refit in Urlampe homeland |
Grant value (excluding GST) | $156,055 |
Current status | Works completed July 2025 |
| Completion report | Read the Urlampe Solar Upgrade completion report PDF (1.3 MB) |
Service provider/contractor | Ecoenergy Australia Pty Ltd |
|---|---|
Proposed work | Solar power refit in Kulpitharra homeland |
Grant value (excluding GST) | $126,100 |
Current status | Works completed November 2025 |
| Completion report | Read the Kulphitarra completion report PDF (1.6 MB) |
Service provider/contractor | Advanced Plumbing and Gas Services |
|---|---|
Proposed work | Septic upgrades in Ilpurla homeland |
Grant value (excluding GST) | $31,831 |
Current status | Works completed May 2025 |
| Completion report | Read the Ilpurla completion report PDF (1.7 MB) |
Service provider/contractor | Bush Grid |
|---|---|
Proposed work | Installation of generator in Banthula homeland |
Grant value (excluding GST) | $131,781 |
Current status | Works completed June 2025 |
| Completion report | Read the Banthula completion report PDF (1.7 MB) |
Service provider/contractor | Ecoenergy Australia Pty Ltd |
|---|---|
Proposed work | Solar power system upgrade in Double D homeland |
Grant value (excluding GST) | $82,047 |
Current status | Works completed November 2025 |
| Completion report | Read the Murray Downs completion report PDF (2.4 MB) |
Service provider/contractor | Laynhapuy Homelands Aboriginal Corporation |
|---|---|
Proposed work | Installation of solar power system in Burrum homeland |
Grant value (excluding GST) | $123,640 |
Current status | Works completed August 2025 |
| Completion report | Read the Burrum house completion report PDF (1.7 MB) |
Service provider/contractor | Tiwi Islands Regional Council |
|---|---|
Proposed work | Solar System upgrade - Paru |
Grant value (excluding GST) | $47,500 |
Current status | Works completed September 2025 |
| Completion report | Read the Paru completion report PDF (3.7 MB) |
Service provider/contractor | Yilli Rreung Housing Aboriginal Corporation |
|---|---|
Proposed work | New Generator - Walangurrminy |
Grant value (excluding GST) | $35,586 |
Current status | Works completed August 2025. |
| Completion report | Read the Walangurrminy generator upgrade completion report PDF (830.1 KB). |
Service provider/contractor | McMinns Bore |
|---|---|
Proposed work | New Bore - Fitzroy Station |
Grant value (excluding GST) | $13,850 |
Current status | Works completed November 2025 |
| Completion report | Read the Bore Overview Fitzroy Station completion report PDF (4.8 MB) |
Service provider/contractor | Warnbi Aboriginal Corporation - Kakadu |
|---|---|
Proposed work | Patonga Airstrip and Mamukala - Water Filtration |
Grant value (excluding GST) | $23,985.33 |
Current status | Due for completion by September 2026 |
| Service provider/contractor | Bush Grid Pty Ltd |
|---|---|
| Proposed work | Upgrades to Solar Power to Gunpura |
| Grant value (excluding GST) | $135,769 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Bullant Building | |
|---|---|---|
| Proposed work | Mulga Bore - Sanitation Upgrades | |
| Grant value (excluding GST) | $140,000 | |
| Current status | Works completed September 2025 | |
| Completion report | Read the Mulga Bore Sanitation Upgrades completion report PDF (7.8 MB) |
| Service provider/contractor | Yapa-Kurlangu Ngurrara Aboriginal Corporation |
|---|---|
| Proposed work | Bonya - Electrical Upgrades |
| Grant value (excluding GST) | $255,218 |
| Current status | Due for completion by June 2026 |
| Service provider/contractor | Territory Water Solutions |
|---|---|
| Proposed work | Burudu - Solar Power Repair |
| Grant value (excluding GST) | $242,165 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Territory Water Solutions |
|---|---|
| Proposed work | Jemelke - Bore and Water Works Upgrades |
| Grant value (excluding GST) | $35,209 |
| Current status | Works completed January 2026 |
| Completion report | Read the Jemelke Bore and Water Works Upgrades completion report PDF (2.2 MB) |
| Service provider/contractor | Urapuntja Aboriginal Corporation |
|---|---|
| Proposed work | Soapy Bore and Atheley – New Waste Site |
| Grant value (excluding GST) | $84,000 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | M.G. Electrical Services Pty Ltd |
|---|---|
| Proposed work | Mulga Bore - Powerline Extension |
| Grant value (excluding GST) | $346,210 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Yilli Rreung Housing Aboriginal Corporation |
|---|---|
| Proposed work | House 5 Wariuk |
| Grant value (excluding GST) | $65,000 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Warnbi Aboriginal Corporation |
|---|---|
| Proposed work | Mudginberri – Bore Works |
| Grant value (excluding GST) | $51,603 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Ngaliwurru-Wuli Aboriginal Corporation |
|---|---|
| Proposed work | Brumby Plains – Septic Upgrades |
| Grant value (excluding GST) | $35,000 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Think Water Alice Springs |
|---|---|
| Proposed work | Wild Plum and Jemelke – Solar Bore and Generator Works |
| Grant value (excluding GST) | $96,612 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Territory Water Solutions |
|---|---|
| Proposed work | Burudu – Solare Bore |
| Grant value (excluding GST) | $115,000 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Laynhapuy Homelands Aboriginal Corporation |
|---|---|
| Proposed work | Bukudal – Septic and Water Tank |
| Grant value (excluding GST) | $72,635 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | McMinns Bore Services |
|---|---|
| Proposed work | Fitzroy Station – Bore Works |
| Grant value (excluding GST) | $16,820 |
| Current status | Due for completion by August 2026 |
| Service provider/contractor | Bawinanga Homelands Aboriginal Corporation |
|---|---|
| Proposed work | Upgrades to Power System in Ji-Marda Homeland |
| Grant value (excluding GST) | $212,760 |
| Current status | Due for completion by August 2026 |