Central Land Council
The latest updates from the Homelands Housing and Infrastructure Program (HHIP) in the Central Land Council.
| Service Provider/Contractor | Tangentyere Constructions |
|---|
| Homelands | Atji Creek, Green Valley, New Bore, Ulambara, Warumpi, Wataru, Tjuntinanta & Ilpili |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $4.360M |
|---|
| Current status | Works to commence July 2026 |
|---|
| Service Provider/Contractor |
Tangentyere Constructions
|
|---|
| Proposed work |
Housing and infrastructure upgrades
|
|---|
| Grant value (excluding GST) |
$3.000M
|
|---|
| Current status |
Works commenced December 2025
|
|---|
Completion reports
| Service Provider/Contractor | The Trustee for the Brian Curran Family Trust (trading as Barkly Plumbing Services) |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $1.800M |
|---|
| Current status | Works commenced February 2026 |
|---|
| Service Provider/Contractor |
Yapa-Kurlangu Ngurrara Aboriginal Corporation
|
|---|
| Proposed work |
Housing and infrastructure upgrades
|
|---|
| Grant value (excluding GST) |
$1.410M
|
|---|
| Current status | Works commenced May 2025
|
|---|
Completion reports
| Service Provider/Contractor |
Aboriginal Enterprises Australia NT
|
|---|
| Proposed work |
Housing and infrastructure upgrades
|
|---|
| Grant value (excluding GST) |
$2.700M
|
|---|
| Current status |
Works commenced November 2025
|
|---|
Completion reports
| Service Provider/Contractor | Bullant Building |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $2.685M |
|---|
| Current status | Works commenced May 2026 |
|---|
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Homelands | Undoolya Bore, Urrermerne, Angkerle Arrange A and Angkerle Arrange B |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $6.855M |
|---|
| Current status | To be confirmed |
|---|
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $940,000 |
|---|
| Current status | To be confirmed |
|---|
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Homelands | Foxalls Well, Spotted Tiger, Mount Eaglebeak and Alatyeye (Turners Camp) |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $2.420M |
|---|
| Current status | To be confirmed |
|---|
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $5.600M |
|---|
| Current status | Works commenced October 2025 |
|---|
Completion reports
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $3.900M |
|---|
| Current status | Works commenced July 2025 |
|---|
Completion reports
| Service Provider/Contractor | Ingkerreke Services Aboriginal Corporation |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $4.415M |
|---|
| Current status | To be confirmed |
|---|
| Service Provider/Contractor |
Thangkenharenge Aboriginal Corporation
|
|---|
| Proposed work |
Housing and infrastructure upgrades
|
|---|
| Grant value (excluding GST) |
$1.655M
|
|---|
| Current status | Works commenced October 2025 |
|---|
Completion reports
| Service Provider/Contractor |
Tjuwanpa Outstation Resource Centre (Aboriginal Corporation
|
|---|
| Proposed work |
Housing and infrastructure upgrades
|
|---|
| Grant value (excluding GST) |
$350,000
|
|---|
| Current status | Works completed May 2025
|
|---|
Completion reports
| Service Provider/Contractor | Urapuntja Aborginal Corporation |
|---|
| Proposed work | Housing and infrastructure upgrades |
|---|
| Grant value (excluding GST) | $2.630M |
|---|
| Current status | Works commenced April 2026 |
|---|